  1. Clean the flange of the casting frame and the top 5-inch area of the cone of the manhole with a wire brush and a whisk broom.  Both areas must be clean and dry.


a
  1. Stretch the Infi-Shield Uniband over the casting and position it so that it will seal from the top of the casting frame's flange to the top of the cone section.  Be sure that the inspection tap is at the top of the seal.

Infi-Shield - Installation
a
  1. Covering the entire adjustment area, fold back the top and bottom mastic portions of the seal.  Apply the aerosol primer on the casting flange and top of the cone where the mastic will bond.  Allow a few minutes for the primer to dry and become tacky.

Infi-Shield - Installation
a
  1. Remove the protective tape from the non-hardening butyl mastic strips

Infi-Shield - Installation
a
  1. Fold the seal back onto the structure.  Press the sealing surfaces together, bonding the Uniband to the flange and the top edge of the cone.  Creating a seal over the entire adjustment ring area.

Infi-Shield - Installation
a

  1. Now using a rubber hammer, tap the sealing surface area.

Infi-Shield - Installation
a

  1. Clean a 5-inch area on the cover with a wire brush.  Position the inspection tab on the side of the casting frame and onto the cover.  Remove the protective tape from the mastic on the free end of the inspection tab and fasten the inspection tab onto the cover tapping it into place with a rubber hammer.

Infi-Shield - Installation
  1. Back fill, now you have a permanent seal between the manhole frame and the cone, including the entire 
    adjustment area.

Infi-Shield - Installation

 

Infi-Shield Seal Wrap Installation

         Ready to printInfi-Shield Seal Wrap Installation (PDF)

  1. Clean the flange of the casting frame and the top 5-inch area of the cone of the manhole with a wire brush and a whisk broom.  Both areas must be clean and dry.


a
  1. Apply a thin coating of the aerosol primer 4” above and below the joint. Allow the primer to dry 1-10 minutes depending on weather conditions. (5 minutes at 70 degrees Fahrenheit)

     


a

  1. Remove the first foot of paper backing from the mastic. Center and place the Seal Wrap around the joint. Continue to remove paper backing as you apply the Seal Wrap to the entire structure. Seal the

    overlapping area with a 4” overlap.

     


a

  1. Using a rubber mallet or hand held roller, firmly flatten the Seal Wrap into its final position. Contact Sealing Systems, Inc. for additional installation instructions or any other product information at  1-800-478-2054.

 

   